Project Details

CROSS, Domestic Biogas

Client Name Community Reconstruction of Social Service
Short Name CROSS
Client Type Grassroots NGO
Synopsis
Address Velkur Village & Post
G.D. Nellore
City Chittoor District
Pin Code 517125
State Andhra Pradesh
Project Title CROSS Biogas CDM Project
Project Description CROSS will build 5,000 domestic biogas units for as many families in Chittoor district
Standard CDM & Gold Standard
Technology Domestic Biogas
Units 5,000
Families 5,000
Methodology AMS-I.E. Switch from Non-Renewable Biomass for Thermal Applications by the User
Estimated Annual ERs 15,000
CDM Contact Bhupathy

Started On 10 January 2011
Activity Processes Touched 12 of 15
Tasks Completed 82 of 140

Task Log

ProcessJobTaskStartEndStakeholderReason
15. Registration 15.3. Webhost for Registration 15.3.5. PDD Registered 28 Feb 1328 Feb 13 UNFCCC  
14. Validating the PDD 14.3. Draft Validation Report 14.3.4. Revise PDD based on Draft Validation Report, CLs & CARs 17 Jul 1217 Jul 12 Tech Team  
14. Validating the PDD 14.3. Draft Validation Report 14.3.2. Prepare Additional Documents & Provide Information to answer CLs and CARs 23 Jun 1216 Jul 12 Project Proponent  
14. Validating the PDD 14.3. Draft Validation Report 14.3.3. Respond to Clarifications (CLs) and Corrective Action Requests (CARs) 23 Jun 1216 Jul 12 Tech Team  
14. Validating the PDD 14.3. Draft Validation Report 14.3.1. Receive Draft Validation Report 22 Jun 1222 Jun 12 Tech Team  
11. Obtaining Gold Standard Certification 11.5. GS Passport & Feedback 11.5.2. Webhost GS Stakeholder Meeting Report and Draft Passport Report for public comments for 60 days 28 May 1228 May 12 Project Proponent  
11. Obtaining Gold Standard Certification 11.5. GS Passport & Feedback 11.5.1. Prepare GS Passport 12 Apr 1224 May 12 Tech Team  
11. Obtaining Gold Standard Certification 11.4. Review of the Stakeholder Meeting Report 11.4.2. Address Issues Raised & Revise GS Stakeholder Meeting Report accordingly 19 Apr 127 May 12 Tech Team  
11. Obtaining Gold Standard Certification 11.4. Review of the Stakeholder Meeting Report 11.4.3. Upload Revised GS Stakeholders Meeting Report onto the GS Registry 7 May 127 May 12 Project Proponent  
11. Obtaining Gold Standard Certification 11.4. Review of the Stakeholder Meeting Report 11.4.1. Receive Comments & Feedbacks from the Gold Standard 18 Apr 1218 Apr 12 Project Proponent  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.4. Upload GS Stakeholders Meeting Report onto the GS Registry 9 Apr 129 Apr 12 Project Proponent  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.5. Prepare Sustainable Development Matrix 1 Jan 126 Apr 12 Tech Team  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.6. Finalise the GS Stakeholder Meeting Report 13 Jan 126 Apr 12 Tech Team  
13. Obtaining Host Country Approval 13.2. Attend Personal Interview with Designated National 13.2.2. List Documents to be Submitted to the DNA 5 Apr 125 Apr 12 DNA  
13. Obtaining Host Country Approval 13.2. Attend Personal Interview with Designated National 13.2.1. Receive Letter from DNA for the Personal Interview 20 Mar 122 Apr 12 Project Proponent & Tech Team  
13. Obtaining Host Country Approval 13.1. Submit PIN & PDD to MoEF 13.1.1. Prepare Project Idea Note (PIN) 20 Mar 122 Apr 12 Tech Team  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.3. Send Signed Copies of GS Agreement to GS Registry 14 Mar 1221 Mar 12 Project Proponent  
14. Validating the PDD 14.1. Appoint a DOE 14.1.3. Submit the PDD for Validation 15 Mar 1215 Mar 12 Project Proponent  
12. Finalising PDD 12.1. Finalise the PDD 12.1.2. Revise PDD based on NGO Feedback 10 Mar 1213 Mar 12 Tech Team  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.1. Explain Procedure to Open an Account at the GS Registry 13 Mar 1213 Mar 12 Tech Team  
11. Obtaining Gold Standard Certification 11.3. Open Account at the GS Registry 11.3.2. Open the Account 13 Mar 1213 Mar 12 Project Proponent  
12. Finalising PDD 12.1. Finalise the PDD 12.1.1. Finalise all Sections of the PDD & Submit to Project Proponent 1 Jun 119 Mar 12 Tech Team  
13. Obtaining Host Country Approval 13.1. Submit PIN & PDD to MoEF 13.1.3. Mail Hard Copies and CDs to MoEF, New Delhi 5 Mar 129 Mar 12 DNA  
14. Validating the PDD 14.1. Appoint a DOE 14.1.2. Appoint a DOE for the project 27 Feb 127 Mar 12 Project Proponent  
8. Proving Additionality (PDD) 8.3. Address Technology Barrier 8.3.1. Make a Literature Scan 24 May 117 Mar 12 Tech Team  
13. Obtaining Host Country Approval 13.1. Submit PIN & PDD to MoEF 13.1.2. Make 20 Hard Copies and 2 CDs of PIN & PDD 5 Mar 125 Mar 12 Project Proponent  
4. Determining Baseline (PDD) 4.4. Calculate expected CERs for the Project 4.4.2. Calculate the emission reduction potential for the project activity 3 Feb 1229 Feb 12 Tech Team  
14. Validating the PDD 14.1. Appoint a DOE 14.1.1. Advise the Project Proponent on Strengths, Capabilities, Fees, etc. of various Validators 25 Feb 1227 Feb 12 Tech Team  
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.1. Describe Institutional Structure of NGO 7 Feb 129 Feb 12 Project Proponent  
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.2. Describe Management Plan for Monitoring 7 Feb 129 Feb 12 Project Proponent  
6. Developing Monitoring Plan (PDD) 6.2. Institutional Structure for Monitoring 6.2.3. Describe Roles & Responsibilities of Monitoring Team 5 Feb 129 Feb 12 Project Proponent  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.1. List Monitoring Parameters 24 Jan 1227 Jan 12 Tech Team  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.2. Determine Monitoring Frequency for these Parameters 24 Jan 1227 Jan 12 Tech Team  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.3. Determine Monitoring Duration of Project Activity 24 Jan 1227 Jan 12 Tech Team  
6. Developing Monitoring Plan (PDD) 6.1. Determine Monitoring Parameters 6.1.4. Determine Maintainence & Servicing Mechanism of the Technology 24 Jan 1227 Jan 12 CDM Preparation Team  
9. Determining Project Duration (PDD) 9.1. Address Project Duration Issues 9.1.1. Anticipate a Realistic Start Date for the CDM Project 24 Jan 1226 Jan 12 Project Proponent  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.1. Provide Proof of Invitation 11 Jan 1225 Jan 12 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.2. Provide Photos of the GS Stakeholders Meeting(s) 11 Jan 1225 Jan 12 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.3. Provide Scanned Copies of Evaluations Forms, Participants List, etc. 11 Jan 1225 Jan 12 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.2. Prepare GS Stakeholders Meeting Report 11.2.4. Translate Sample Evaluation Forms from Local Language into English 11 Jan 1225 Jan 12 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.9. Conduct GS Stakeholders Meeting(s) 9 Jan 129 Jan 12 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.9. Conduct GS Stakeholders Meeting(s) 9 Jan 129 Jan 12 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.8. Place Newspaper Ads & Send Out Invitations with Support Documents 15 Dec 118 Jan 12 CDM Preparation Team  
4. Determining Baseline (PDD) 4.4. Calculate expected CERs for the Project 4.4.1. Analyse Baseline Data for PDD 26 Dec 112 Jan 12 Tech Team  
4. Determining Baseline (PDD) 4.3. Conduct Baseline Survey(s) 4.3.4. Enter data in Microsoft Excel sheet 6 Dec 1131 Dec 11 CDM Preparation Team  
4. Determining Baseline (PDD) 4.3. Conduct Baseline Survey(s) 4.3.3. Collect Household Data using the Finalised Format & Procedure 4 Dec 1128 Dec 11 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.5. Translate Texts into Local Language 8 Dec 1114 Dec 11 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.6. Decide on Date(s) & Venue(s) for the GS Stakeholder Meeting(s) 1 Dec 1110 Dec 11 Project Proponent  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.4. Prepare Draft Invitation Letters & Emails, Write-ups, Posters, matter for Newpaper Ads, etc. 27 Nov 118 Dec 11 Tech Team  
4. Determining Baseline (PDD) 4.2. Design Sample Survey Format 4.2.4. Make changes in questionnaire if required 7 Dec 117 Dec 11 Tech Team  
4. Determining Baseline (PDD) 4.2. Design Sample Survey Format 4.2.6. Analyse the data 7 Dec 117 Dec 11 Tech Team  
4. Determining Baseline (PDD) 4.2. Design Sample Survey Format 4.2.5. Enter data in Microsoft Excel sheet 3 Dec 116 Dec 11 CDM Preparation Team  
4. Determining Baseline (PDD) 4.2. Design Sample Survey Format 4.2.3. Field test in 50 households 1 Dec 112 Dec 11 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.3. Translate Non-technical summary into Local Language 25 Nov 111 Dec 11 CDM Preparation Team  
3. Collecting Demographic Data 3.3. Collect Demographic Data 3.3.3. Analyse Data for PDD 26 Nov 1130 Nov 11 CDM Preparation Team  
3. Collecting Demographic Data 3.3. Collect Demographic Data 3.3.1. Collect Household Data 1 Jul 1125 Nov 11 CDM Preparation Team  
3. Collecting Demographic Data 3.3. Collect Demographic Data 3.3.2. Enter Data into the Module & Retain Survey Sheets till Validation 1 Jul 1125 Nov 11 CDM Preparation Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.2. Prepare Non-Technical Summary 21 Nov 1125 Nov 11 Tech Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.7. Assist in Drawing up Invitation List 25 Nov 1125 Nov 11 Tech Team  
11. Obtaining Gold Standard Certification 11.1. Conduct GS Stakeholder Meeting 11.1.1. Familiarise CDM Team & NGO Staff on Procedure 19 Nov 1119 Nov 11 Tech Team  
4. Determining Baseline (PDD) 4.3. Conduct Baseline Survey(s) 4.3.1. Prepare Sampling Plan Document with detailed Instructions 19 Nov 1119 Nov 11 Tech Team  
4. Determining Baseline (PDD) 4.3. Conduct Baseline Survey(s) 4.3.2. Determine Sample Size for Baseline Survey 19 Nov 1119 Nov 11 Tech Team  
4. Determining Baseline (PDD) 4.2. Design Sample Survey Format 4.2.2. Translate into Local Language 4 Nov 115 Nov 11 CDM Preparation Team  
4. Determining Baseline (PDD) 4.2. Design Sample Survey Format 4.2.1. Design Test Questionnaire 1 Nov 112 Nov 11 Tech Team  
3. Collecting Demographic Data 3.1. Design Questionnaire 3.1.3. Administer the Questionnaire to about 50 Households 1 Jun 116 Jul 11 CDM Preparation Team  
3. Collecting Demographic Data 3.1. Design Questionnaire 3.1.5. Analyse the Data 9 Jun 119 Jun 11 Tech Team  
3. Collecting Demographic Data 3.1. Design Questionnaire 3.1.4. Enter data in Microsoft Excel 7 Jun 117 Jun 11 CDM Preparation Team  
1. Deciding to Undertake CDM 1.1. Develop Comfort Level 1.1.3. Explain Process, Cost & Timeframe to Develop a CDM Project 23 May 1123 May 11 Tech Team  
1. Deciding to Undertake CDM 1.3. Decide to Undertake CDM 1.3.2. Assemble a CDM Preparation Team & Appoint Contact Person 23 May 1123 May 11 Project Proponent  
2. Selecting CDM Project 2.2. Choose Methodology 2.2.2. Determine the baseline scenario in the project area 23 May 1123 May 11 Tech Team  
2. Selecting CDM Project 2.2. Choose Methodology 2.2.3. Determine if Baseline Satisfies Applicability Criteria of the Methodology 23 May 1123 May 11 Tech Team  
2. Selecting CDM Project 2.2. Choose Methodology 2.2.4. Calculate Approximate Scale of Project Activity 23 May 1123 May 11 Tech Team  
3. Collecting Demographic Data 3.1. Design Questionnaire 3.1.2. Translate to Local Language 22 May 1122 May 11 CDM Preparation Team  
3. Collecting Demographic Data 3.1. Design Questionnaire 3.1.1. Design Preliminary Questionnaire 21 May 1121 May 11 Tech Team  
1. Deciding to Undertake CDM 1.1. Develop Comfort Level 1.1.2. Explain Implications in Dealing with Commercial Moneys 15 May 1115 May 11 FCN Convenor  
1. Deciding to Undertake CDM 1.2. Assess Capacity 1.2.1. Study Organisational Structure and Assess Implementation Capacity 28 Mar 1129 Mar 11 Tech Team  
1. Deciding to Undertake CDM 1.2. Assess Capacity 1.2.2. Assess Staying Capacity and Intimacy with Communities 28 Mar 1129 Mar 11 Tech Team  
1. Deciding to Undertake CDM 1.2. Assess Capacity 1.2.3. Share Findings with the NGO Leadership 28 Mar 1129 Mar 11 FCN Convenor  
2. Selecting CDM Project 2.1. Identify Technologies 2.1.2. Suggest & Explain Possible Technologies 28 Mar 1128 Mar 11 Tech Team  
2. Selecting CDM Project 2.1. Identify Technologies 2.1.3. Determine Feasibility of Technology vis-à-vis Resource Avaibility & Absorbtion Capacity 28 Mar 1128 Mar 11 NGO Leadership  
2. Selecting CDM Project 2.2. Choose Methodology 2.2.1. Scan CDM Methodologies for Identified Technologies 28 Mar 1128 Mar 11 Tech Team  
2. Selecting CDM Project 2.3. Decide Project Boundary 2.3.1. Decide on Geographic Boundary & Scale of Project Activity 14 Feb 1114 Feb 11 Project Proponent  
1. Deciding to Undertake CDM 1.1. Develop Comfort Level 1.1.1. Visit running CDM Project & Learn from Experienced Stakeholders 10 Jan 1111 Jan 11 NGO Leadership